@article{oai:kyutech.repo.nii.ac.jp:00004218, author = {出口, 近士 and Yoshitake, Tetsunobu and 吉武, 哲信 and 佐多, 孝徳 and 浅野, 誠}, issue = {3}, journal = {都市計画論文集}, month = {Oct}, note = {Land readjustment projects have various risks derived from many landowners and long project term. Therefore it is very important for completing land readjustment projects to identify and evaluate the risks from the view of project management. This paper firstly discusses the identification by use of AHP based on a questionnaire to land readjustment planners and engineers who have more than 2years experiments.Thirty seven risks were identified among 4 project stages and the risks were compared with eight categories of an exist research for DID area comparisons show good agreements. And the weights of the risks to financial crisis obtained by AHP were found not to have differences from the knowledge of land readjustment experts. These results suggest that the identified risks and their weight are useful for risk or project management of land readjustment project.}, pages = {271--276}, title = {土地区画整理事業におけるリスク特定と影響度の評価 -組合施行を対象として-}, volume = {44}, year = {2009}, yomi = {ヨシタケ, テツノブ} }